One question per page, answered directly. Written for people keeping site records on Australian projects.
What is a contemporaneous record in construction?
A contemporaneous record is one made at the time of the event it describes, by somebody who was there, rather than reconstructed afterwards. In construction it matters because delay, variation and payment disputes are usually assessed months later, when memory has gone and the people involved have moved on.
Read the full answerWhat should a site diary contain?
At minimum: the date and weather, who was on site, what work was committed and whether it happened, why anything did not happen, deliveries and their times, plant and equipment, instructions received, and anything that stopped or delayed work. The reason a task did not proceed is the entry most diaries record badly and the one most often needed later.
Read the full answerWhat do adjudicators look for in site records?
Records made at the time rather than assembled for the claim, covering every day rather than only the disputed ones, consistent enough that a pattern can be counted, and specific about what happened, when, and what it affected. Volume is not the test. An adjudicator working to a statutory timetable is looking for records that make the point quickly and can be relied on.
Read the full answer